605 Lexington Development Update

2019-01-23T21:30:46+00:00 January 23rd, 2019|Uncategorized|

Construction of Selwyn Property Group’s 605 Lexington Avenue office building is progressing nicely. All the structural steel is in place, and the metal framing for the building exterior is well underway. Landmark Builders has performed well in the face of a very wet winter. At this point they still plan to complete the shell building in late March/early April. The tenant upfits for Merriman Schmitt/Orsborn Engineering and Selwyn Property Group should commence in early March, providing for occupancy in late April/early May.

As construction has progressed, leasing activity has also picked up for the two vacant spaces in the building- 2,500 SF on the first floor and 6,600 SF on the second floor.